Category: Quantities & pricing
Prepared by Eng. Ahmed Fathy, Projects Manager ·
Definition
Net measured quantity is the work quantity under the contract measurement rules after applicable deductions. It differs from procurement quantity, which may include cutting, waste and overlaps not separately measured.
Why it matters on a project
It prevents double counting waste and distinguishes payment quantities from purchasing requirements.
Measurement and pricing
Check measurement boundaries, units, openings and returns. Record waste in procurement or rate analysis as required by the item scope.
Worked example
Net floor area is 80 m² with an assumed procurement cutting allowance of 7%: extra is 80 × 7 ÷ 100 = 5.6 m² and procurement need is 80 + 5.6 = 85.6 m² before pack rounding. Measured item quantity remains 80 m² under this example's basis.
Common mistake
Adding waste to the measured item quantity and allowing for the same waste again in the unit rate.
Frequently asked questions
Is net quantity always below procurement?
Usually where cutting and waste apply, but align scope and units before comparing.
Is waste a fixed percentage?
No. It depends on layout, sizes and construction method; document the assumptions.
Related terms
- Method of measurementThe agreed rules for measuring each BOQ item.
- Waste allowanceA percentage added to material quantities to cover cutting, damage and site loss.
- Measurement sheetA sheet recording the dimensions and calculation behind each quantity.
Read next
- Quantity Takeoff for Contractors, Step by Step
- Work out quantities with our free calculators: concrete, tiles, paint and plaster. Open the calculators
Does your project need quantity take-off and BOQ pricing? Send the drawings or a short description and we reply within one working day.
Service detailsRequest a quote