Net measured quantity

الكمية الصافية المقاسة

Work quantity after applying the agreed measurement and deduction rules.

Category: Quantities & pricing

Prepared by Eng. Ahmed Fathy, Projects Manager ·

Definition

Net measured quantity is the work quantity under the contract measurement rules after applicable deductions. It differs from procurement quantity, which may include cutting, waste and overlaps not separately measured.

Why it matters on a project

It prevents double counting waste and distinguishes payment quantities from purchasing requirements.

Measurement and pricing

Check measurement boundaries, units, openings and returns. Record waste in procurement or rate analysis as required by the item scope.

Worked example

Net floor area is 80 m² with an assumed procurement cutting allowance of 7%: extra is 80 × 7 ÷ 100 = 5.6 m² and procurement need is 80 + 5.6 = 85.6 m² before pack rounding. Measured item quantity remains 80 m² under this example's basis.

Common mistake

Adding waste to the measured item quantity and allowing for the same waste again in the unit rate.

Frequently asked questions

Is net quantity always below procurement?

Usually where cutting and waste apply, but align scope and units before comparing.

Is waste a fixed percentage?

No. It depends on layout, sizes and construction method; document the assumptions.