Concurrent delay

التأخير المتزامن

Owner and contractor delays in the same period, both affecting completion.

Category: Contracts & management

Prepared by Eng. Ahmed Fathy, Projects Manager ·

Definition

Concurrent delay occurs when an owner-risk delay and a contractor-risk delay happen in the same period, and each alone would have delayed completion. The contract decides how it is treated, and much practice grants extension of time without money.

Why it matters on a project

It is the most argued point in delay claims. Analysis of the updated programme and site records decides it, not general impressions.

Common mistake

A contractor claiming full costs for an owner delay while its own labour was short in the same period.

Frequently asked questions

How is concurrent delay shown?

By analysing the updated programme and daily labour and plant records for the same period.

Does the contractor get paid?

It depends on the contract; much practice gives time only, without costs.