Extension of time (EOT)

تمديد المدة

The contractor’s entitlement to additional time for delay not of its making, subject to timely notice.

Category: Contracts & management

Prepared by Eng. Ahmed Fathy, Projects Manager ·

Definition

An extension of time is a formal increase in contract duration for events outside the contractor's responsibility, such as variations, late owner approvals or exceptional conditions.

Why it matters on a project

It is proven by analysing the event's effect on the critical path of the programme, not by stating that a delay happened.

Common mistake

Claiming time without tying it to the approved programme and the critical activities affected.

Frequently asked questions

What supports an extension claim?

A timely notice, site records and an analysis of the event's effect on the approved programme.

Does an extension mean money too?

Not always; some events give time only, others time and cost, depending on the contract.

Related terms

  • Critical pathThe sequence of activities where any delay delays project completion.
  • Baseline programmeThe programme approved at project start against which progress is measured.
  • Delay damages (liquidated damages)An agreed sum deducted per day of delay after the contractual completion date, capped in the contract.
  • Variation order (VO)A written instruction changing scope, quantity or specification, with its price and time effect.