Baseline programme

خط الأساس

The programme approved at project start against which progress is measured.

Category: Contracts & management

Prepared by Eng. Ahmed Fathy, Projects Manager ·

Definition

The baseline programme is the schedule approved at the start of the project, with its activities, durations and logic, against which progress and delay are measured.

Why it matters on a project

Without an approved baseline, delay cannot be proven and extensions cannot be claimed. It is usually prepared in Primavera P6.

Common mistake

Building a programme with large summary activities and too little detail, so it cannot track progress or analyse delay.

Frequently asked questions

Which software is used for the programme?

Primavera P6 is the most requested on large and government projects; MS Project on smaller ones.

Is the baseline changed?

No. The current programme is updated and compared with it; a new baseline needs formal approval.