Category: Contracts & management
Prepared by Eng. Ahmed Fathy, Projects Manager ·
Definition
A time impact analysis inserts an event fragnet and relationships into an appropriate schedule and compares results. Review progress status, calendars, constraints, concurrency and the contractually relevant method.
Why it matters on a project
Event duration does not automatically equal completion delay.
Measurement and pricing
Preserve before-and-after files, assumptions, fragnet and scheduling logs, explaining path and finish changes.
Worked example
In a simplified common-calendar network with zero-lag finish-to-start links, parallel paths take 20 and 17 working days. Adding a 5-day event to the shorter path gives 17 + 5 = 22 days, changing finish by 22 − 20 = 2 working days. This illustrates logic, not an extension decision.
Common mistake
Adding event duration directly to project finish without network analysis.
Frequently asked questions
Does one method suit every claim?
Method depends on contract, assessment timing, records and event characteristics.
Does it remove the need to assess concurrency?
No. Assess relevant concurrent events and constraints under a defined method.
Related terms
- Extension of time (EOT)The contractor’s entitlement to additional time for delay not of its making, subject to timely notice.
- Critical pathThe sequence of activities where any delay delays project completion.
- Concurrent delayOwner and contractor delays in the same period, both affecting completion.
Read next
Does your project need engineering consultancy and project management? Send the drawings or a short description and we reply within one working day.
Service detailsRequest a quote