Category: Contracts & management
Prepared by Eng. Ahmed Fathy, Projects Manager ·
Definition
Contemporary records include daily reports, labour, plant, photographs, instructions and tests. Link them to time, location and activity while preserving originals and revision history.
Why it matters on a project
They help distinguish observed events from later estimates of their effects.
Measurement and pricing
Reconcile dates and identifiers with schedules, quantities and correspondence, identifying gaps and contradictions.
Worked example
A record shows 8 workers for 6 hours on a defined activity: total is 8 × 6 = 48 labour-hours. This does not classify all hours as idle or compensable without evidence of condition and cause.
Common mistake
Presenting a retrospective reconstruction as an original event-time record.
Frequently asked questions
Are photographs alone sufficient?
Link them to location, date, activity and relevant supporting records.
How is a reconstructed record identified?
Label it as a reconstruction with preparation date, sources and limitations, preserving originals.
Related terms
- Contractual claimA formal request for money or time under the contract.
- Progress reportA periodic report of what was done, what slipped and why.
- Notice of claimA contractual notice identifying an event that may support a claim.