Definition
Prolongation cost depends on delay cause, entitlement, contract provisions and actual evidence. It differs from changed-work cost and disruption and does not follow automatically from an extension of time.
Why it matters on a project
Separating categories helps avoid recovering the same expense twice.
Measurement and pricing
Link costs to periods, resources and cause, checking prior recovery, exclusions and contract requirements.
Worked example
A documented additional period is 10 days. The site office remained throughout, but an item of plant left after day four. Assess each resource's continuation and entitlement separately rather than assigning plant presence to all ten days.
Common mistake
Multiplying all daily overheads by the extension without proving continuation or causation.
Frequently asked questions
Does an extension automatically give financial compensation?
No. Review terms, delay causes and cost evidence.
Does this include disruption?
Disruption may require a different claim and analysis, with no double recovery.
Related terms
- Extension of time (EOT)The contractor’s entitlement to additional time for delay not of its making, subject to timely notice.
- Indirect costs (overheads)Site and head-office costs not attributable to a single item, added as a percentage.
- Contemporary recordsRecords created at or near an event to document facts.