Definition
Release follows contract percentages, stages, certificates, defects status and account reconciliation. Conditions vary; handover does not automatically release all retention.
Why it matters on a project
Separating retained, certified-for-release and paid amounts avoids overstating the balance.
Measurement and pricing
Reconcile deductions, releases and payments with certificates, contract conditions and any other adjustments.
Worked example
For percentages only, retention equals 5% of a fixed calculation base and an assumed contract permits release of half that balance. The released amount is 5% × 0.5 = 2.5% of the base, leaving retention of 5% − 2.5% = 2.5% of the base. The retention rate therefore falls by 2.5 percentage points. Neither the percentage nor the release stage is universal.
Common mistake
Calculating release from the original contract sum instead of checking actual retention records.
Frequently asked questions
Is all retention released at handover?
The agreed stages, conditions and certificates govern.
Does released mean cash received?
No. Distinguish certified release from actual transfer.
Related terms
- RetentionA percentage withheld from each payment and released after handover or the defects period.
- Handover certificateA document evidencing the client’s acceptance of the works and start of the defects period.
- Final accountThe final financial settlement of the contract value after completion.