Category: Contracts & management
Prepared by Eng. Ahmed Fathy, Projects Manager ·
Definition
Reconciliation brings together contract basis, adjustments, measurement and agreed claims, then distinguishes payments, deductions, retention and applicable tax treatment. Keep disputed items visible.
Why it matters on a project
Final work value differs from the remaining cash balance.
Measurement and pricing
Check each adjustment reference, prevent duplicate changes or advance recovery, and reconcile certificates.
Worked example
A reconciliation has 24 adjustments, with 21 supported and 3 outstanding: 24 − 21 = 3 unresolved adjustments. Arithmetic completion alone does not close the account review.
Common mistake
Confusing certified value with actual cash paid or concealing unsettled items.
Frequently asked questions
Is the final account just the last application?
Its adjustments, statements and agreement status may differ under the contract.
How are unsettled claims shown?
Keep them separately identified rather than presenting them as agreed value.
Related terms
- Final accountThe final financial settlement of the contract value after completion.
- Payment application (IPC)A periodic payment request based on approved progress and executed quantities.
- Variation registerA register tracking changes, references, impacts and approval status.