Category: Contracts & management
Prepared by Eng. Ahmed Fathy, Projects Manager ·
Definition
A variation register assigns each change an identifier and links instructions, valuation, time effects and correspondence. Distinguish proposed, submitted, agreed, executed and paid states.
Why it matters on a project
It prevents lost changes and duplicate payment entries.
Measurement and pricing
Reconcile it with instructions, payment applications, programme records and measurement references.
Worked example
A register has 18 changes: 7 agreed, 6 being assessed and 5 without submitted valuations, totalling 7 + 6 + 5 = 18. Unagreed changes total 6 + 5 = 11; track execution and payment separately.
Common mistake
Combining proposed and approved amounts without status separation.
Frequently asked questions
Should a rejected change be deleted?
Retain it with the reason and date for traceability.
Does executed mean its value is agreed?
No. Execution and financial agreement are separate statuses.
Related terms
- Variation order (VO)A written instruction changing scope, quantity or specification, with its price and time effect.
- Variation valuationAssessing a change's financial effect under contract rules and evidence.
- Payment application (IPC)A periodic payment request based on approved progress and executed quantities.