Total float

السماح الزمني الكلي

Time difference between early and late dates under scheduling settings.

Category: Contracts & management

Prepared by Eng. Ahmed Fathy, Projects Manager ·

Definition

Total float reflects schedule flexibility under the network, dates and constraints. In P6 check whether calculation uses start float, finish float or the smaller value; it does not establish contractual ownership.

Why it matters on a project

Constraints and calendars can change float without changing work quantity.

Measurement and pricing

Review early and late dates, scheduling logs, calculation settings, constraints and calendars.

Worked example

On a common working-day axis without calendar differences or additional constraints, early start is day 10 and late start day 14: start float is 14 − 10 = 4 days. It represents total float here only where the calculation setting and condition use that basis.

Common mistake

Assuming positive float makes an activity irrelevant to completion regardless of subsequent logic changes.

Frequently asked questions

Does the contractor own the float?

The computed value does not determine ownership; consult the contract for that question.

Does negative float prove responsibility?

No. It reflects scheduling and constraints and requires causal interpretation.

Related terms

  • Critical pathThe sequence of activities where any delay delays project completion.
  • Baseline programmeThe programme approved at project start against which progress is measured.
  • Free floatDelay available without delaying immediate successors' early dates.