Free float

السماح الزمني الحر

Delay available without delaying immediate successors' early dates.

Category: Contracts & management

Prepared by Eng. Ahmed Fathy, Projects Manager ·

Definition

Free float depends on successor relationships and calendars. Multiple relationship types mean that simply subtracting two displayed dates may be insufficient.

Why it matters on a project

An activity can have total float but no flexibility before delaying the next trade.

Measurement and pricing

Review all successors, relationships, lags and calendars against the scheduled activity result.

Worked example

With one calendar and a zero-lag finish-to-start relationship, an activity finishes at time boundary 8 and its successor starts at boundary 11: free float is 11 − 8 = 3 working days, assuming no tighter successor.

Common mistake

Adding free and total float as separate delay allowances.

Frequently asked questions

Can free float be zero while total float is positive?

Yes. Delay may move a successor without moving project finish.

Is the first successor enough to check?

No. Review all controlling relationships and calendars.

Related terms

  • Total floatTime difference between early and late dates under scheduling settings.
  • Relationship lagA time offset applied to a relationship between activities.
  • Critical pathThe sequence of activities where any delay delays project completion.