Category: Contracts & management
Prepared by Eng. Ahmed Fathy, Projects Manager ·
Definition
Lag offsets a relationship such as finish-to-start. Review units, the lag calendar and P6 settings; represent measurable work as an activity where it needs independent tracking.
Why it matters on a project
Hiding a long procurement wait in lag makes responsibility and progress difficult to track.
Measurement and pricing
Check relationship type, lag sign, calendar and scheduled effect with predecessors and successors visible.
Worked example
On a continuous working-day axis, predecessor finish is boundary 5 and positive finish-to-start lag is 2 days: this link permits start at 5 + 2 = 7. Other relationships or constraints may delay it further.
Common mistake
Assuming a day-based lag always means calendar days.
Frequently asked questions
Is lag an activity?
No. It is a relationship property without independent activity tracking.
Does it always use the predecessor calendar?
Check the schedule's lag-calendar setting rather than assuming one option.
Related terms
- Baseline programmeThe programme approved at project start against which progress is measured.
- Free floatDelay available without delaying immediate successors' early dates.
- Remaining activity durationExpected working time to finish the remaining activity scope.