Category: Contracts & management
Prepared by Eng. Ahmed Fathy, Projects Manager ·
Definition
Remaining duration is a current estimate based on quantities, resources, constraints and productivity. It need not equal original duration times incomplete percentage; review P6 activity settings.
Why it matters on a project
High reported progress can still leave a test or delivery controlling completion.
Measurement and pricing
Relate outstanding scope to realistic productivity, access, resources, approvals and calendar.
Worked example
Remaining plaster is 240 m² at assumed crew output 40 m² per working day: net production duration is 240 ÷ 40 = 6 days. Review approvals, access, drying and sequence before adopting the schedule duration.
Common mistake
Automatically reducing duration despite an unresolved execution constraint.
Frequently asked questions
Must duration fall in proportion to progress?
No. Productivity, constraints and remaining scope can change.
Does it include holidays?
Duration uses working-time units; the calendar maps these to dates.
Related terms
- Labour productivityThe amount of work a worker or crew completes per day.
- Schedule data dateThe status date separating recorded progress from remaining work.
- Look-ahead scheduleA short-term detailed plan for the next three or four weeks.