Schedule data date

تاريخ بيانات البرنامج

The status date separating recorded progress from remaining work.

Category: Contracts & management

Prepared by Eng. Ahmed Fathy, Projects Manager ·

Definition

The data date anchors scheduling and status updates. Coordinate it with the reporting cut-off; it is not automatically the date a file is opened or printed.

Why it matters on a project

Comparing different data dates without disclosure can suggest misleading progress.

Measurement and pricing

Check actual dates and quantities up to cut-off, then schedule and preserve settings.

Worked example

A report covers through the end of 18 November with a data date at the start of 19 November. Record only achieved progress up to cut-off and treat later expectations as remaining work, stating the convention.

Common mistake

Moving the data date without updating progress or remaining durations.

Frequently asked questions

Does printing change the data date?

No. It is a status setting within the schedule.

Can expected progress be recorded as actual?

No. Keep evidenced facts distinct from forecasts.