Category: Contracts & management
Prepared by Eng. Ahmed Fathy, Projects Manager ·
Definition
The data date anchors scheduling and status updates. Coordinate it with the reporting cut-off; it is not automatically the date a file is opened or printed.
Why it matters on a project
Comparing different data dates without disclosure can suggest misleading progress.
Measurement and pricing
Check actual dates and quantities up to cut-off, then schedule and preserve settings.
Worked example
A report covers through the end of 18 November with a data date at the start of 19 November. Record only achieved progress up to cut-off and treat later expectations as remaining work, stating the convention.
Common mistake
Moving the data date without updating progress or remaining durations.
Frequently asked questions
Does printing change the data date?
No. It is a status setting within the schedule.
Can expected progress be recorded as actual?
No. Keep evidenced facts distinct from forecasts.
Related terms
- Progress reportA periodic report of what was done, what slipped and why.
- Baseline programmeThe programme approved at project start against which progress is measured.
- Remaining activity durationExpected working time to finish the remaining activity scope.