Category: Contracts & management
Prepared by Eng. Ahmed Fathy, Projects Manager ·
Definition
This occurs, for example, when a finish-to-start successor starts before its predecessor finishes. Determine whether logic is wrong or execution changed, then document the appropriate treatment.
Why it matters on a project
Retained logic and progress override can produce different remaining dates and completion forecasts.
Measurement and pricing
Review actual facts, relationships and scheduling logs against the real execution plan.
Worked example
Painting starts before its plastering predecessor finishes under a finish-to-start link. Check whether completed rooms justify location-based activity splitting, documenting the revision rather than arbitrarily deleting logic.
Common mistake
Changing scheduling options merely to hide delay without documenting the reason.
Frequently asked questions
Does it always mean site work is wrong?
Logic may be over-aggregated or the method changed; review the facts.
Is progress override always better?
No. Use a treatment representing the real remaining plan and disclose its effect.
Related terms
- Schedule data dateThe status date separating recorded progress from remaining work.
- Relationship lagA time offset applied to a relationship between activities.
- Progress reportA periodic report of what was done, what slipped and why.