Out-of-sequence progress

التقدم خارج تسلسل البرنامج

Actual progress occurring contrary to recorded schedule logic.

Category: Contracts & management

Prepared by Eng. Ahmed Fathy, Projects Manager ·

Definition

This occurs, for example, when a finish-to-start successor starts before its predecessor finishes. Determine whether logic is wrong or execution changed, then document the appropriate treatment.

Why it matters on a project

Retained logic and progress override can produce different remaining dates and completion forecasts.

Measurement and pricing

Review actual facts, relationships and scheduling logs against the real execution plan.

Worked example

Painting starts before its plastering predecessor finishes under a finish-to-start link. Check whether completed rooms justify location-based activity splitting, documenting the revision rather than arbitrarily deleting logic.

Common mistake

Changing scheduling options merely to hide delay without documenting the reason.

Frequently asked questions

Does it always mean site work is wrong?

Logic may be over-aggregated or the method changed; review the facts.

Is progress override always better?

No. Use a treatment representing the real remaining plan and disclose its effect.