Baseline update control

ضبط تحديث خط الأساس

Controlling changes to the schedule reference through a documented process.

Category: Contracts & management

Prepared by Eng. Ahmed Fathy, Projects Manager ·

Definition

Progress updates change the current schedule; changing a baseline alters the comparison reference and follows the agreed control process. Preserve the prior version, reason, scope and any required approval.

Why it matters on a project

Replacing the reference at every update hides historical variance.

Measurement and pricing

Compare versions, dates, activities, costs or weights and baseline assignments used in reports.

Worked example

An original baseline finishes at working-day boundary 100 and the current forecast at 112 on the same axis: variance is 112 − 100 = 12 days. Replacing the baseline with the forecast hides this comparison; preserve the reference and controlled revision separately.

Common mistake

Treating an available P6 update command as contractual authorization.

Frequently asked questions

Does progress updating change the reference?

Keep the operations distinct and check the assigned baseline.

Can a revised baseline be approved?

Under the applicable process and agreement, preserving versions and reasons.

Related terms

  • Baseline programmeThe programme approved at project start against which progress is measured.
  • Drawing revisionA number and date that identify each changed version of a drawing.
  • Progress reportA periodic report of what was done, what slipped and why.