Definition
Resource loading assigns labour, plant or other resources using consistent units, calendars and productivity. Check the interaction with activity type, duration and unit distribution in P6.
Why it matters on a project
A logically valid schedule can still require more labour than available.
Measurement and pricing
Reconcile units with quantities and productivity and review demand profiles, peaks and availability conflicts.
Worked example
An activity needs 240 labour-hours with 5 workers at 8 hours daily: daily capacity is 5 × 8 = 40 labour-hours, giving 240 ÷ 40 = 6 days with constant productivity and availability.
Common mistake
Confusing worker count with labour-hours or treating cost loading as a labour plan.
Frequently asked questions
Does doubling workers always halve duration?
No. Space, interference, supervision and sequence can limit productivity.
Should peaks be checked?
Yes. Aggregate concurrent demand and compare it with available resources.
Related terms
- Labour productivityThe amount of work a worker or crew completes per day.
- Baseline programmeThe programme approved at project start against which progress is measured.
- Equipment costThe cost of plant used in the work, hired or owned.