Category: Contracts & management
Prepared by Eng. Ahmed Fathy, Projects Manager ·
Definition
SPI compares earned and planned value at a defined date. It does not measure critical-path delay in days, and aggregation can mask a sensitive activity's delay.
Why it matters on a project
A strong index can coexist with late low-weight critical procurement.
Measurement and pricing
Check weighting, earned-progress rules, data date and baseline, assessing critical path separately.
Worked example
On a fixed weighted-progress scale, planned value is 60 units and earned value 48 units: SPI is 48 ÷ 60 = 0.8. This does not mean project completion is delayed by 20% of its duration.
Common mistake
Converting the index directly into days of extension entitlement.
Frequently asked questions
Does it measure the critical path?
No. Assess schedule logic and critical path separately.
Is it valid with zero planned value?
Division by zero is undefined; report it as not calculable.
Related terms
- Earned valueA method that measures progress and cost together against the plan.
- S-curveA cumulative progress or cost curve over time.
- Critical pathThe sequence of activities where any delay delays project completion.