Definition
Weights may use cost, labour-hours or another agreed basis. Apply them to consistently measured progress and distinguish the result from cash-payment curves when the basis differs.
Why it matters on a project
A simple activity-percentage average gives a small task and a major package equal importance.
Measurement and pricing
Check total weights, scope coverage, double counting and earning rules for each activity.
Worked example
Two packages have weights 40% and 60% and progress 50% and 25%: earned proportion is 0.4 × 0.5 + 0.6 × 0.25 = 0.35, or 0.35 × 100 = 35%. Weights use a fixed agreed basis.
Common mistake
Changing weights during reporting to improve the result without controlled reference changes.
Frequently asked questions
Can progress percentages simply be added?
No. Multiply each by its weight and sum on one basis.
Is cash flow the same as progress?
Not necessarily; advances, retention and payment terms change cash flow.
Related terms
- S-curveA cumulative progress or cost curve over time.
- Earned valueA method that measures progress and cost together against the plan.
- Progress reportA periodic report of what was done, what slipped and why.