Definition
A recovery programme revisits sequence, resources, working time, procurement, constraints and tests. Show each measure's effect, risks and required approvals without rewriting actual history.
Why it matters on a project
Shortened bars do not prove available work fronts or approvals.
Measurement and pricing
Check productivity, capacity, congestion, calendars, critical path and differences from the previous update.
Worked example
For 300 m² remaining, assumed output 30 m²/day gives 300 ÷ 30 = 10 days. A 6-day target needs 300 ÷ 6 = 50 m²/day, subject to feasible productivity and resources without omitting tests.
Common mistake
Deleting necessary activities or logic simply to achieve a target date.
Frequently asked questions
Is adding a shift sufficient?
Check lighting, safety, supervision, productivity, permissions and interference.
Does it erase earlier delay?
No. Preserve actual history and show the remaining recovery plan.
Related terms
- Look-ahead scheduleA short-term detailed plan for the next three or four weeks.
- Resource-loaded programmeA schedule with resource quantities and time distributions assigned to activities.
- Critical pathThe sequence of activities where any delay delays project completion.