Recovery programme

برنامج استدراك التأخير

An updated plan showing feasible measures to reduce delay.

Category: Contracts & management

Prepared by Eng. Ahmed Fathy, Projects Manager ·

Definition

A recovery programme revisits sequence, resources, working time, procurement, constraints and tests. Show each measure's effect, risks and required approvals without rewriting actual history.

Why it matters on a project

Shortened bars do not prove available work fronts or approvals.

Measurement and pricing

Check productivity, capacity, congestion, calendars, critical path and differences from the previous update.

Worked example

For 300 m² remaining, assumed output 30 m²/day gives 300 ÷ 30 = 10 days. A 6-day target needs 300 ÷ 6 = 50 m²/day, subject to feasible productivity and resources without omitting tests.

Common mistake

Deleting necessary activities or logic simply to achieve a target date.

Frequently asked questions

Is adding a shift sufficient?

Check lighting, safety, supervision, productivity, permissions and interference.

Does it erase earlier delay?

No. Preserve actual history and show the remaining recovery plan.