Prepared by Eng. Ahmed Fathy, Projects Manager ·
Definition
A refrigeration ton measures heat-removal rate, approximately 3.517 kW of cooling. Electrical input is different and depends on efficiency and operating conditions.
Why it matters on a project
Confusing cooling kW with electrical kW can misinform cable and protective-device selection.
Measurement and pricing
Convert capacity consistently and review actual cooling and electrical data separately.
Worked example
Using the rounded conversion 3.517 kW cooling per ton, 3 tons equals 3 × 3.517 = 10.551 kW nominal cooling. Obtain electrical input separately from selection data.
Common mistake
Assuming a three-ton unit necessarily consumes three electrical kilowatts.
Frequently asked questions
Does a ton specify equipment mass?
No. It is a thermal-capacity unit.
Is nominal capacity always available?
Check project conditions, outdoor temperature and piping installation.
Related terms
- Cooling loadThe heat the air conditioning must remove from a space.
- Electrical load scheduleA table summing each board's loads to size breakers, cables and the meter.
- Air-conditioner capacity correctionAdjusting rated capacity for actual selection conditions.