Category: Safety & quality
Prepared by Eng. Ahmed Fathy, Projects Manager ·
Definition
Inspection closeout links each comment to its location, correction evidence, reinspection and authorized response. Completing work is not closure where verification or acceptance remains required.
Why it matters on a project
It prevents open issues from passing into concealment or handover without traceability.
Measurement and pricing
Match comments to identified photographs, results or measurements and record item status, acceptance date and closing authority.
Worked example
A list has 40 comments, of which 34 are verified closed: open items are 40 − 34 = 6 and closure is 34 ÷ 40 × 100 = 85%. Report critical comments separately because the percentage does not measure consequence.
Common mistake
Marking an item closed solely on the contractor's completion statement without the required verification.
Frequently asked questions
Can a comment be reopened?
Yes, if verification shows incomplete treatment or recurrence; preserve its history.
Can one general photograph close every item?
No. Evidence must match each location, requirement and inspection method.
Related terms
- Inspection request (IR)A formal request from the contractor to the consultant to inspect work before the next stage.
- Snag list (punch list)A list of incomplete or defective items to be completed before final handover.
- NCR (non-conformance report)A report recording work or material not meeting the specification, with root cause and corrective action.