Category: Safety & quality
Prepared by Eng. Ahmed Fathy, Projects Manager ·
Definition
A witness point gives the designated party an opportunity to attend a notified inspection or test. The inspection plan and procedure define what happens if they do not attend; permission to proceed is not assumed.
Why it matters on a project
It organizes attendance at important checks while remaining distinct from a hold point.
Measurement and pricing
Record notification time, test date, response, attendance or accepted waiver and the technical result.
Worked example
The consultant is notified of a test within the project notice period. If absent, follow the procedure for proceeding or rescheduling and retain both the actual result and notification evidence.
Common mistake
Treating no response as acceptance of a test that was never performed or recorded.
Frequently asked questions
Is there a universal notice period?
No. The relevant plan, procedure or contract defines it.
Does absence cancel the test?
No. The technical need remains; attendance and execution follow the procedure.
Related terms
- Inspection and test planA schedule defining activity checks, acceptance criteria, responsibilities and records.
- Hold pointA stage beyond which work cannot proceed without the specified release.
- Inspection request (IR)A formal request from the contractor to the consultant to inspect work before the next stage.
Read next