Category: Safety & quality
Prepared by Eng. Ahmed Fathy, Projects Manager ·
Definition
A hold point stops the work sequence until the inspection or approval specified by the authorized party is completed. The procedure defines how release is given and recorded.
Why it matters on a project
It prevents concealment or pouring before checks that would be difficult afterward.
Measurement and pricing
Check inspection notice, records, outstanding comments and release authority before the next stage.
Worked example
The pour plan makes reinforcement and opening inspection a hold point. Concrete arrival does not change that status; pouring needs the specified release and closure of blocking comments.
Common mistake
Proceeding because an inspector did not attend without documented authorization to release the hold point.
Frequently asked questions
Can it be bypassed to avoid delaying a truck?
Not without the procedure's required release by the authorized party.
Where is release recorded?
In the approved inspection record with date, identity and status.
Related terms
- Inspection and test planA schedule defining activity checks, acceptance criteria, responsibilities and records.
- Pre-pour checklistChecking steel, formwork and services before a pour is approved.
- Inspection request (IR)A formal request from the contractor to the consultant to inspect work before the next stage.