Definition
A setting-out grid relates drawing grid identifiers to site control. It records offsets of columns and walls from grid axes; an element centreline need not coincide with a gridline.
Why it matters on a project
It avoids cumulative measurement from an incorrectly built element and provides a shared checking reference.
Measurement and pricing
Check coordinates, overall and intermediate dimensions, orientation and suitable diagonals, then independently verify set-out points before construction.
Worked example
A gridline is at easting 500.000 m and a column centre is offset 0.150 m east: column centre is 500.000 + 0.150 = 500.150 m. Check offset and direction against the drawing before setting out.
Common mistake
Setting a wall from a column face without checking column offset and finish thickness.
Frequently asked questions
Is every column centred on a grid intersection?
No. Check offsets and sizes on the set-out drawing and column schedule.
Are diagonal checks sufficient?
They help but do not replace coordinates, lengths, orientation and site control.
Related terms
- Site planA drawing showing the building within the plot with setbacks, entrances and levels.
- Column scheduleA table giving each column type's size and reinforcement on each floor.
- Shop drawingsDrawings prepared by the contractor or fabricator showing how items are made and installed, approved by the consultant before execution.
Read next
Does your project need architectural design and construction drawings? Send the drawings or a short description and we reply within one working day.
Service detailsRequest a quote