Category: Contracts & management
Prepared by Eng. Ahmed Fathy, Projects Manager ·
Definition
Rectification identifies location, condition, cause, consequences and responsibility under the procedure and contract. Select the repair, assess adjacent systems and repeat required checks.
Why it matters on a project
Painting a damp stain can hide evidence without resolving water ingress.
Measurement and pricing
Link each item to its repair method, before-and-after evidence, retest and accepted closure date.
Worked example
A list has 18 defects; 14 were repaired and reinspected but only 12 accepted closed: open items are 18 − 12 = 6. The two unaccepted repairs remain open.
Common mistake
Treating elapsed time as proof of repair or automatic extinction of rights without applicable contract and legal review.
Frequently asked questions
Is an after-repair photograph enough?
Depending on the defect, measurement, testing or monitoring may be needed to verify the cause is resolved.
Does closeout cancel every warranty?
Do not infer that from the register; review acceptance scope, contract terms and applicable requirements.
Related terms
- Snag list (punch list)A list of incomplete or defective items to be completed before final handover.
- Inspection comment closeoutRecording inspection comment resolution and authorized acceptance of closure.
- Defects liability periodThe period after handover during which the contractor must repair defects at its own cost.