Category: Design
Prepared by Eng. Ahmed Fathy, Projects Manager ·
Definition
The duty point specifies required flow and head; actual operation follows the pump-system interaction and controls. Check efficiency, allowable range and multiple-pump arrangements.
Why it matters on a project
Separate maximum-head and maximum-flow figures do not establish performance at the required duty.
Measurement and pricing
Locate the duty on the curve at the stated speed and measure flow and pressure during testing.
Worked example
A design demand of 2 L/s converts to 2 × 3.6 = 7.2 m³/h. For calculated head 35 m, verify performance at 7.2 m³/h and 35 m together, not at separate curve extremes.
Common mistake
Assuming two parallel pumps double actual flow without checking the system curve.
Frequently asked questions
Can selection use motor kW alone?
No. Motor power does not replace flow, head and efficiency selection.
Is the point tested on site?
Yes, using suitable instruments and a documented system condition.
Related terms
- Pump total dynamic headThe head added by a pump to meet system requirements and losses.
- Underground water tankA concrete tank below ground for storing drinking water.
- Testing and commissioningA documented process verifying system readiness and operating performance.