Definition
Reinforcement cutting length is the length of unbent steel required to make the bar shape in the bending schedule. It depends on dimension conventions, bend diameters, hooks and specified laps.
Why it matters on a project
It directly affects ordered mass and whether the fabricated bar fits within the required cover.
Measurement and pricing
Check the shape code and whether dimensions are internal, external or along the bar centreline. Apply bend allowances using the approved scheduling convention.
Worked example
A straight bar fits a 4.00 m concrete dimension with 0.04 m end cover each side and no hooks or laps: cutting length is 4.00 − 0.04 − 0.04 = 3.92 m. Ten bars total 10 × 3.92 = 39.20 m. The detail is assumed approved for this example.
Common mistake
Adding external dimensions of a bent bar and treating the sum as an exact cutting length without bend adjustments.
Frequently asked questions
Should every bar receive a lap allowance?
Only where an approved detail contains a lap, without counting it twice.
Does the example prove adequate anchorage?
No. It calculates geometric cutting length; anchorage adequacy is a design matter.
Related terms
- Bar bending schedule (BBS)A schedule listing the diameter, length, shape and number of reinforcement bars per element.
- Reinforcement (rebar)Steel bars placed inside concrete per bar-bending schedules to strengthen structural elements.
- Concrete coverThe concrete thickness between the surface and the nearest bar.
Read next
Does your project need structural design and reinforcement drawings? Send the drawings or a short description and we reply within one working day.
Service detailsRequest a quote