Category: Structure & materials
Prepared by Eng. Ahmed Fathy, Projects Manager ·
Definition
Rebar mass per metre converts scheduled lengths into mass. It can be estimated from section area and steel density, with final values checked against product tables and applicable tolerances.
Why it matters on a project
It supports a diameter-based steel check instead of relying on a rough steel-to-concrete ratio.
Measurement and pricing
Multiply scheduled lengths for each diameter by its mass per metre, then total the diameters. Avoid adding laps or waste already included in the lengths.
Worked example
For estimating, use the approximate relation of diameter in millimetres squared divided by 162: a 16 mm bar gives 16 × 16 ÷ 162 = 1.58 kg/m. For 120 m using the rounded value: 120 × 1.58 = 189.6 kg. This is an approximate theoretical value to check against the product table.
Common mistake
Using the unit mass of a nearby bar diameter or confusing kilograms with tonnes.
Frequently asked questions
Is calculated mass the delivered mass?
It is theoretical. Check delivered mass, product certification and specification at receipt.
Are stirrups included?
Yes, using their scheduled cutting lengths and diameters, not column height.
Related terms
- Bar bending schedule (BBS)A schedule listing the diameter, length, shape and number of reinforcement bars per element.
- Reinforcement cutting lengthThe developed length needed to fabricate an approved bar shape.
- Quantity take-offExtracting quantities from drawings under defined measurement rules, with a reference for every figure.