Category: Contracts & management
Prepared by Eng. Ahmed Fathy, Projects Manager ·
Definition
A handover register tracks as-built drawings, operation and maintenance manuals, test results, warranties and training required by the contract. It links each record to its system or equipment, revision and review status.
Why it matters on a project
It supports owner operation and maintenance and exposes missing records before handover.
Measurement and pricing
Reconcile requirements with installed equipment and identifiers, open the files and check indexes, links and drawing updates.
Worked example
A handover list requires 30 records: 24 accepted, 4 under review and 2 missing, so 24 + 4 + 2 = 30. Records without final acceptance total 4 + 2 = 6; submission is not acceptance.
Common mistake
Delivering a generic catalogue for a different installed model or a file list without its actual documents.
Frequently asked questions
Is sending a large folder enough?
No. Provide an index tied to contract requirements, installed equipment and record status.
When should preparation start?
During construction, keeping it updated rather than chasing missing certificates and equipment identifiers at the end.
Related terms
- As-built drawingsDrawings updated to match what was actually built, handed over in the close-out file.
- Handover certificateA document evidencing the client’s acceptance of the works and start of the defects period.
- WarrantyA commitment to repair defects or replace materials for a set period.