Category: Design
Prepared by Eng. Ahmed Fathy, Projects Manager ·
Definition
A clearance clash occurs when separation is smaller than the space required for insulation, installation or maintenance. The threshold depends on purpose and system requirements rather than one universal value.
Why it matters on a project
A duct may physically fit while leaving no space to install its insulation or remove adjacent equipment.
Measurement and pricing
Measure the relevant clear separation and establish whether insulation is modelled or included in the clearance requirement.
Worked example
The example test plan requires 50 mm clearance, but 32 mm is available between external surfaces: shortfall is 50 − 32 = 18 mm. The 50 mm value is an example requirement, not a universal limit.
Common mistake
Counting insulation twice, once in the model geometry and again in the test threshold.
Frequently asked questions
Is no intersection enough?
No. Insulation, movement or maintenance may require additional space.
Is clearance measured from the pipe centreline?
Normally from the relevant surfaces. Centreline measurements require correct radius and insulation adjustments.
Related terms
- Clash detectionChecking models to find where disciplines collide before construction.
- Equipment access clearanceSpace needed to reach equipment and remove its components safely.
- Hard clashAn actual geometric intersection between two model objects.